In the city centre area, several major changes will be implemented as the extension of the tramway to Pirkkala and Linnainmaa, the renewal of the Tampere railway station area, the renovation of Puutarhakatu and Aleksis Kiven katu and the renovation of Paasikivenkatu are progressing as planned. The first tram rails have been installed on Hatanpää highway and decks have been cast for the most important bridges.
– After the construction of the Hämeenkatu tramway, 2025 has been the most exceptional year for traffic in the city centre. This time too, the people of Tampere have shown their ability to adapt to the exceptional arrangements and work has progressed as planned. Despite the construction sites, the city centre is still accessible by all modes of transport, says Milko Tietäväinen, Director of Construction for the City of Tampere.
Traffic in the city centre has flown mostly like normal, except for peak commuter times. Feedback on projects has been responded to where possible and the worst problems have been mitigated. Exceptionally, traffic was particularly congested during the European Basketball Championships, but the traffic closures caused by this major event were quickly reviewed and traffic returned to normal the following day.
– The combined impact of the projects on traffic has been assessed and efforts have been made to minimise the adverse effects: for example, the extension of the tram network and the renovation of the Tampere railway station area significantly impact on the conditions for the development of the city and therefore there has been no desire to delay them for different times, adds Mikko Nurminen, Director of the Urban Environment and Infrastructure Services.
Several street works will be completed in 2026
The work is progressing on schedule for all mentioned sites. This means that in 2026, people in Tampere will be able to cross the renovated Erkkilä bridge and enjoy improved cycling and walking conditions on Puutarhakatu and Paasikivenkatu. Work on Aleksis Kivi Street and Satakunnankatu will also be completed during 2026.
Puutarhakatu will be opened to through traffic during the winter
During the summer of 2025, the water and sewer pipes on Puutarhakatu were replaced, district cooling pipes built and district heating pipes renovated. At the same time, the pavement has been improved and rock has been excavated to make way for the pipelines. In addition, underground electricity cables and telecoms networks have been upgraded and street lighting has been replaced. As part of the renovation work, the housing associations have had damp proofing carried out on the foundation walls.
During the rest of the year, all underground piping and street lighting will be completed. The first layer of will be asphalted, and some of the pavements will receive new tiles and kerbs. During the winter break, Puutarhakatu will be reopened to through traffic. Surface works will continue in the spring and the entire street reconstruction will be completed during 2026.
Work on Aleksis Kiven katu in the home stretch, traffic will return to normal by the end of the year
Progress has been made on Aleksis Kiven katu with the construction of the drainage structures and retaining wall. Cable ducts have been added, kerbs and natural stone paving have been installed. The carriageway has already been partially paved, and asphalting, street and traffic lights and concrete paving will be completed during the rest of the year. Traffic will return to normal by the end of the year. The remaining paving work on Satakunnankatu will be completed in summer 2026.
No changes to traffic on Paasikivenkatu for the rest of the year
On Paasikivenkatu, a new pedestrian crossing between Sepänkatu and the new Särkänniemi junction has been built during the autumn, together with the new road lanes in accordance with the new alignment.
In early November, a lane closure lasting a few weeks ended, after which one lane in each direction is now available for vehicle traffic. There are currently no known changes affecting traffic for the rest of the year.
Next year, work will continue with district heating and surface works, and the Paasikivenkatu project will be completed in autumn 2026. Greening works will continue until spring 2027, but will not affect vehicle traffic.
Tramway construction is progressing as planned
The Tampere Tramway route is currently being extended towards Pirkkala and Linnainmaa.
– In the first year, our work has focused on municipal engineering: we have renewed and relocated water supply and sewer lines for example, as well as cable routes in the area of the future tram line. In the autumn, we were able to start laying the rails and completed the first sections of street in Härmälä and Partola. The bridge renewal work is also progressing well on the bridges in Viinikanlahti, Vihilahti and Härmälänoja, says Sari Valjus, Project Manager of the Pirkkala-Linnainmaa Alliance of the Tampere Tramway.
Tramway rails have been installed at the intersection of Hatanpää highway and Tampere highway, at Nuolialanantie in Härmälä and in the Tays area in Kaupinlaakso. During the rest of the year, tramway rails will also be built in Härmälänranta.