Renovation of Puutarhakatu

An excavator at the Puutarhakatu construction site at the eastern end of the street.
Puutarhakatu will be renovated between the parks Vanhankirkonpuisto and Hämeenpuisto. The renovation started in March 2025 and continues until 2026. The renovation is being carried out because the water and sewer pipes have reached the end of their useful life and need to be replaced. District cooling pipes will also be built on the street.

After the renovation, the street will have a wider two-way cycle track on the northern edge, pavements on both sides and a one-way carriageway for motor vehicles. The renovation will improve walking and cycling conditions and road safety, and make the street a more pleasant environment. The management of stormwater, i.e. rainwater and meltwater, will also be improved.

Getting around and shopping on Puutarhakatu right now

The renovation of Puutarhakatu has started on 3.3.2025 from the intersections of Näsilinnankatu, Kuninkaankatu and the section between Kuninkaankatu and Aleksis Kiven katu The work will cause traffic disruptions, but the properties will be accessible by all means of transport. Through traffic on the street will be blocked during the excavation work on the carriageway. Pedestrians and cyclists will be able to travel between Aleksis Kiven katu and Hämeenpuisto.

Working hours start at 6 a.m. and end at 22 p.m. However, on Fridays, work will end at 19.30. On Saturdays, construction work will take place from 9 am to 5.30 pm due to increased maintenance and servicing needs. The installation of municipal infrastructure continues.

Construction site in the week starting 8.12.

Work has progressed at both Hämeenpuisto and the end of the City Hall on the Puutarhakatu construction site. Water supply trenches are progressing as planned, and the end well of the storm water line has been installed. The work areas have been tidied up and the access routes have been standardized.

Work continues at both ends of the Puutarhakatu construction site. The excavation of load-bearing growing media for tree planting also continues between Kuninkaankatu and Aleksis Kiven katu.

Due to connections at the construction site, there will be another water outage, which will mainly affect properties on Kuninkaankatu and Satakunnankatu. A separate notice will be issued about the outage once the schedule has been agreed with the water utility's working group.

Traffic arrangements:

You can turn right from Puutarhakatu onto Hämeenpuisto, even though information to the contrary was provided last week. Traffic traveling north-south on Hämeenpuisto is single-lane at the Puutarhakatu intersection.

Traffic on Puutarhakatu is one-way between Kuninkaankatu and Hämeenpuisto from east to west.

Excavation and other work areas will restrict motor vehicle traffic on Puutarhakatu. For pedestrians and cyclists, Puutarhakatu is passable, but the routes used will change as the work areas move. Please follow signs and signposted routes. The map shows the routes for motor vehicles.

Traffic on Näsilinnankatu and Kuninkaankatu flows in one direction between Kauppakatu and Satakunnankatu; on the Kuninkaankatu section towards Satakunnankatu and on the Näsilinnankatu section towards Kauppakatu.

Between Kuninkaankatu and Aleksis Kiven katu, the Puutarhakatu properties are accessed via Kuninkaankatu. From Aleksis Kiven katu there is no turning onto Puutarhakatu.

Aleksis Kiven katu has been changed to a one-way street from Kauppakatu to Satakunnankatu, so that Satakunnankatu provides access to the parking garage at Frenckellinaukio, but no further.

If necessary, please contact the construction site by e-mail [email protected].

The map shows the motor vehicle traffic routes in the area affected by the works. Pedestrians and cyclists will be able to pass through Puutarhakatu, and cyclists will not be affected by the one-way streets.

Traffic arrangements on the map from 5.12.2025.
Traffic arrangements at the Puutarhakatu construction site on the map. Motor vehicle routes are marked in blue.

The aim is to renovate as much as possible in one go, in cooperation between the different actors, so as to cause as little inconvenience as possible and in as short a time as possible.

The renovation of the City Hall and the construction of a new building at the corner of Puutarhakatu and Aleksis Kiven katu are also underway. City Hall and its new building will be completed in spring 2026. 

Cyclists and walkers on the left, cars on the right on the street and at a stop.
View of Puutarhakatu after the renovation. (Photo: Ramboll)

Contact us

You can ask questions or give feedback about the Puutarhakatu project and the future construction site by email: [email protected]

Your message will be forwarded to the right person.

Project actors

The City of Tampere is the main developer of the Puutarhakatu project. Tampere Water, Tampereen Energia Oy, Tampereen Energia Sähköverkko Oy and telecom operators are also involved. Tampereen Infra Oy is the main contractor of the project.  Puutarhakatu will be renewed in cooperation between the parties involved.

The renovation of Puutarhakatu will allow properties bordering the street to improve the accessibility of entrances, for example by removing low thresholds and stairs. 

Mikko Siiro
Construction of a street, commissioned by the City of Tampere: Construction engineer
Phone:
041 731 1568
Petri Kantola
Construction of a street, commissioned by the City of Tampere:
Phone:
050 364 6095
Timo Seimelä
Traffic planning, commissioned by the City of Tampere:
Pasi Palmu
Street design, commissioned by the City of Tampere:
Phone:
040 801 6812
Jukka Palonperä
Water management works, Tampere Water: Construction engineer
Phone:
050 413 1885
Karo Kilpinen
Electrical cables, district heating and district cooling, commissioned by Tampereen Energia Oy:
Phone:
040 773 9165
Juho Riikonen
Contractor, Tampereen Infra:
Phone:
041 731 0942
Aaro Liukko-Sipi
Contractor, Tampereen Infra: Foreman
Phone:
041 731 0798
Updated 8.12.2025